Runways and Airfield
Soekarno-Hatta has three runways aligned north-east–south-west: two parallel main runways and a third runway added in 2019.
Key facts
| Detail | Information |
|---|---|
| Directions | 07R/25L, 07L/25R and 06/24 |
| Longest runway | 07R/25L — 3,660 m |
| Second runway | 07L/25R — 3,600 m |
| Third runway | 06/24 — 3,000 m |
| Surface | Asphalt |
Runway directions
The runways are designated by their compass directions: 07R/25L and 07L/25R for the parallel pair, and 06/24 for the third runway.
Runways in detail
| Runway | Length | Notes | Status |
|---|---|---|---|
| 07R/25L | 3,660 m | Northern parallel runway | In use |
| 07L/25R | 3,600 m | Southern parallel runway | In use |
| 06/24 | 3,000 m | Third runway, operational since 15 August 2019 | In use |
Capacity and taxiways
- The apron can serve up to 60 aircraft, up from 40 before the Terminal 3 expansion.
- The east cross taxiway, opened in December 2019, links the two main runways.
- Aircraft movements rose from 72 to 86 per hour after the east cross taxiway opened.
Airfield development
The third runway and the east cross taxiway were completed under the airport’s expansion programme.
Plans for a fourth terminal were scrapped in November 2024 in favour of optimising the existing terminals.